What they’re really checking

The reviewer wants evidence that your team has rehearsed a disruption and knows how long it takes to get the service and its data back.

What a good answer looks like

Example to adapt with your own details

We maintain a business continuity and disaster recovery plan for [service]. The last exercise took place on [date] and covered [scenario] in [environment]. The team restored [systems and data], then verified [customer workflows and reconciliation checks]. Recovery took [measured time] against a [time target]. The latest usable recovered data was [age] against a [data-loss target]. The exercise identified [gaps], with actions owned by [roles] and due [dates]. The attached report records the results and what was outside scope. Our next exercise is scheduled for [date] under [the agreed cadence or plan].

Give the business continuity and technical recovery results separately where the exercises had different scopes. For continuity, the reviewer may want to know whether staff could keep essential work going and communicate with the buyer. For technical recovery, show that the service and its data were usable again under the tested conditions.

Explain the start and end of your timing in the report. If the clock stopped when the database came back, say so. If it stopped when a representative transaction went through and was reconciled, record that too. Those results answer different questions about what the buyer can expect.

Record any help the exercise relied on. If the team restored using a supplier or specialist who was only available during working hours, include that dependency. If recovery took longer than planned, record which step ran over and the change you’re making. Give the reviewer the retest result when you have one.

Evidence to send

  • The current plan with an owner, escalation contacts, scenarios, recovery order, dependencies and targets for the buyer’s service.
  • The latest exercise report with the date, scenario, environment, participants, actual results and what was outside scope.
  • A recovery timeline, restore records and checks showing key transactions work after recovery. Record the data point you recovered to and compare it with when the disruption began.
  • A list of missed targets, manual workarounds and follow-up actions, with owners and evidence from any retest.

What to do if you can’t answer yet

  1. Pick a scenario based on the service the bank will use and work out which parts have to return first. A restored database may be only the first step. The buyer may also need a working API, queues, keys, supplier access and reconciled transactions.
  2. Agree two targets with whoever owns the service. A recovery time objective (RTO) is how long you aim to be down. A recovery point objective (RPO) is how much recent data you’re designing around, expressed as time before the disruption. Record what you measured as well as what the plan promises.
  3. Run a safe exercise in an approved environment. Record the start time and define what counts as recovery before you begin. Include the steps that verify the service works, such as processing a representative workflow or reconciling test records. When using a representative environment, explain what differs from production.
  4. Call a tabletop a tabletop. It’s useful for checking roles and decisions. A restore or failover exercise supplies separate evidence of technical recovery. If you’ve only run one kind of exercise or missed the interval the buyer requested, explain the gap and report any confirmed next test date.

Who asks this

Enterprise buyers, insurers, UK banks and insurers, US banks and BaaS sponsors, and EU banks and insurers can ask for this. The US banking agencies’ guide lists continuity and disaster recovery test results as potential evidence. DORA Article 30(3)(c) addresses tested contingency plans in contracts for ICT services supporting critical or important functions. Confirm the cadence against the specific buyer’s requirements.

Related questions

This is general guidance. It does not constitute legal or audit advice.

Talk to a cloud expert

Optional analytics help us understand how the site is used. You can accept or decline them. Your preference is saved on this device.

Read the cookie notice